פרוייקטים
Zaporizhye Steel III
YWCT was awarded with a contract to design and deliver a cooling tower for a steel mill in Ukraine. The cooling tower was designed to fit an existing basin which was revamped for this purpose and was conceived of five cells (two + three), m12Xm12 each. Erection was conducted locally in less than three months, just in time before cold winter (up to -35Co) was coming.