Hod Assaf approached our company with a request to replace two old cooling towers that had been serving as part of the production system at the company’s plant in Acre. The existing towers were installed above a shared concrete basin. Since the cooling towers were a critical component of the production process, the replacement had to be carried out within an exceptionally short timeframe during the plant’s annual shutdown. To meet the tight schedule, the new towers were designed in a modular configuration, prefabricated at our facility, and delivered to site for a fast, precise, and efficient replacement.

Year
2025
Construction
Pultruded fiberglass
Water flow
2,000 m³hr