Our company, in collaboration with our local distributors in Ukraine, won the replacement project for an old Natural Draft cooling tower. In order to save space and make the most of the old cooling tower area, our company designed a three-cell tower that fits exactly half of the area. The old tower was dismantled, a partition between the pool sections was built, and inside the new pool, the new tower was constructed, consisting of three cells, each measuring 13m x 13m

Year
2018
Construction
Pultruded fiberglass
Water flow
8,000 m³hr