On one of Israel’s tallest buildings, YWCT was asked to replace a 30-year-old cross-flow cooling tower.

Site conditions were tough: The given footprint was small, surrounded by walls of a new luxury residential complex planned for the top floor.

YWCT designed a special three-basin-level, double-cross-flow cooling tower, each of whose five 6 m cells was equipped with a special fan to kept noise levels to a minimum for the comfort of the penthouse residents.

Year

2007

Construction

Pultruded FRP

Water flow

2,000 m³/hr

Industry

HVAC